2024 Paving Program

Paving Rehabilitation

REVIEWED/REVISED: 7/02/24

Brookhaven, GA, April 1, 2024 Competitive bids were opened on February 21, 2024, answering an invitation to contractors to bid on a three-year paving program for the City of Brookhaven. This award encompasses the paving program for the 2024, 2025, and 2026 years respectively. Over the three years specified, this project will impact 76 streets and 42.81 lane miles of Brookhaven roadways, and utilize SPLOST II (Special Purpose Local Option Sales Tax) funding.

**CW Matthews was awarded the three-year contract by the Brookhaven City Council on March 26, 2024.**

 

NOTICE!

 

THERE WILL BE NO ASPHALT OPERATIONS PERFORMED FROM JULY 1, 2024, TO JULY 6, 2024.*

*Operations will resume on Monday, July 8, 2024, on Cravenridge Drive.

 

THE START/END DATES ON THE SCHEDULE CAN CHANGE DAILY, PLEASE SEE THE MOST UPDATED SCHEDULE, BELOW.

 

 ROADWAY MILLING AND RESURFACING OPERATIONS WILL INCLUDE MOST SATURDAYS!

 

2024 BROOKHAVEN ASPHALT PAVING SCHEDULE: UPDATED 07/02/24
START DATE* END DATE* STREET NAME FROM STREET TO STREET WORK TYPE
           
05/28/24 05/28/24 FERNWAY COURT BYRNWYCK ROAD CUL-DE-SAC MILL & OVERLAY ASPHALT
BY 06/15/24 BRETON CIRCLE WOODROW WAY RENNES DRIVE MILL & OVERLAY ASPHALT
05/31/24 06/03/24 WOOD VALLEY COURT JOHNSON FERRY ROAD CUL-DE-SAC MILL & OVERLAY ASPHALT
BY 06/15/24 FRONTENAC COURT WOODROW WAY CUL-DE-SAC MILL & OVERLAY ASPHALT
BY 06/15/24 CLUB WALK DRIVE HERMANCE DRIVE CUL-DE-SAC MILL & OVERLAY ASPHALT
06/18/24 06/20/24 HERMANCE DRIVE TRAFFIC CIRCLE @ BROOKHAVEN AVENUE MILL & OVERLAY ASPHALT
06/20/24 06/22/24 CALDWELL ROAD DRESDEN DRIVE CHESHIRE WAY MILL & OVERLAY ASPHALT
06/24/24 06/28/24 REDDING ROAD CALDWELL ROAD  END OF ROAD (SOUTH) MILL & OVERLAY ASPHALT
06/28/24 07/10/24 CRAVENRIDGE DRIVE TRYON ROAD (S) CALDWELL ROAD MILL & OVERLAY ASPHALT
07/11/24 07/12/24 SKYLAND DRIVE SKYLAND TRAIL DRESDEN DRIVE MILL & OVERLAY ASPHALT
07/11/24 07/13/24 CANMONT DRIVE** SKYLAND DRIVE CLAIRMONT ROAD MILL & OVERLAY ASPHALT
07/13/24 07/15/24 RAVEN HILL DRIVE** STOLAND DR CLAIRMONT ROAD MILL & OVERLAY ASPHALT
07/15/24 07/16/24 GARDENSIDE COURT SKYLAND TRAIL DEAD END MILL & OVERLAY ASPHALT
07/16/24 07/18/24 EWING DRIVE CORTEZ LANE DREW VALLEY ROAD MILL & OVERLAY ASPHALT
07/18/24 07/19/24 PINECONE LANE DOUBLEGATE DRIVE DEAD END MILL & OVERLAY ASPHALT
07/19/24 07/20/24 LOGAN CIRCLE BRIARWOOD ROAD DEAD END MILL & OVERLAY ASPHALT
07/22/24 07/23/24 LANIER DR (S'BOUND)** WINDSOR PARKWAY PEACHTREE ROAD MILL & OVERLAY ASPHALT
07/23/24 07/24/24 CLUB PLACE MABRY ROAD CUL-DE-SAC MILL & OVERLAY ASPHALT
07/24/24 07/26/24 HAVENBROOK WAY OSBORNE ROAD CUL-DE-SAC MILL & OVERLAY ASPHALT
07/26/24 07/26/24 HARTS MILL ROAD ASHFORD-DUNWOODY ROAD WASSON WAY MILL & OVERLAY ASPHALT
07/27/24 07/29/24 CHIPPEWA PLACE** NAVAJO TRAIL CHIPPEWA PL (CUL-DE-SAC MILL & OVERLAY ASPHALT
07/30/24 08/02/24 CANDLER LAKE WEST W NANCY CREEK DR LONG BRANCH COURT MILL & OVERLAY ASPHALT
07/22/24 07/24/24 LONG BRANCH COURT CANDLER LAKE WEST CUL-DE-SAC FULL-DEPTH RECLAMATION
    MURPHY CANDLER COURT CANDLER LAKE WEST CUL-DE-SAC MILL & OVERLAY ASPHALT
    CRANTON COURT BERKFORD CIRCLE CUL-DE-SAC MILL & OVERLAY ASPHALT
    BRAWLEY WAY BRAWLEY WAY/BRAWLEY CR BERKFORD CIRCLE MILL & OVERLAY ASPHALT
    BRAWLEY CIRCLE BRAWLEY WAY/BRAWLEY CR (LOOPS) MILL & OVERLAY ASPHALT
    DUNWOODY TRAIL VICTOR ROAD DUNWOODY PLACE MILL & OVERLAY ASPHALT
REMOVED E. DREW VALLEY ROAD DREW VALLEY ROAD (N) DREW VALLEY ROAD (S) RESURFACING BY DEKALB CO.
* START/END DATES ARE TENTATIVE BASED ON WEATHER CONDITIONS AND OTHER UNFORESEEN CIRCUMSTANCES AND ARE SUBJECT TO CHANGE.
** A PORTION OF THIS WORK, AS SCHEDULED, FALLS ON A SATURDAY.
           
  ROADWAYS IN PROGRESS.
  CURRENTLY SCHEDULED 2024 ROADWAYS: START DATE AND TIMES ARE TENTATIVE.
  COMPLETED 2024 ROADWAYS.
  FUTURE 2024 ROADWAYS.
JUST ADDED STREETS ADDED TO SCHEDULE AS OF 6/28/24

 

 

* IF RESIDING ON A SCHEDULED ROADWAY, YOU WILL BE NOTIFIED, VIA HANDBILL, 48 HOURS BEFORE OPERATIONS BEGIN.
** MOST ASPHALT OPERATIONS WILL BE COMPLETED IN ONE TO TWO DAYS.
 
*** THE PAVING ACTIVITY WILL AFFECT LOCAL TRAFFIC AND LIMIT DRIVEWAY ACCESS TO HOMES DURING STATED WORKING HOURS; HOWEVER, THE CITY AND THE CONTRACTOR SHALL WORK TO MINIMIZE THIS INCONVENIENCE.
**** RESIDENTS AFFECTED BY ASPHALT OPERATIONS SHALL NOT PARK ON THE STREET BETWEEN ESTABLISHED WORKING HOURS (7 AM - 7 PM).
***** VEHICLES PARKED IN STREETS DURING ASPHALT OPERATIONS ARE SUBJECT TO TOWING AT VEHICLE OWNER'S EXPENSE.

The adopted roads are listed in the following (tables or attachments), by year,

2024 (Phase 1): All 29 streets listed are to be milled and overlayed with 3-inches of asphalt, except for Murphy Candler Court, which will be a Full-Depth-Reclamation (FDR) process.

2025 (Phase 2): All 28 streets listed are to be milled and overlayed with 3-inches of asphalt, except for Ashton Woods Drive, Durden Dive, and Sunderland Way, which will be a Full-Depth-Reclamation (FDR) process.

2026 (Phase 3): All 19 streets listed are to be milled and overlayed with 3-inches of asphalt.

 For more detail on the meaning of each in the process, follow this link to see Brookhaven’s Pavement Restoration Program Details Explained