2024 Paving Program
REVIEWED/REVISED: 7/02/24
Brookhaven, GA, April 1, 2024 – Competitive bids were opened on February 21, 2024, answering an invitation to contractors to bid on a three-year paving program for the City of Brookhaven. This award encompasses the paving program for the 2024, 2025, and 2026 years respectively. Over the three years specified, this project will impact 76 streets and 42.81 lane miles of Brookhaven roadways, and utilize SPLOST II (Special Purpose Local Option Sales Tax) funding.
**CW Matthews was awarded the three-year contract by the Brookhaven City Council on March 26, 2024.**
NOTICE!
THERE WILL BE NO ASPHALT OPERATIONS PERFORMED FROM JULY 1, 2024, TO JULY 6, 2024.*
*Operations will resume on Monday, July 8, 2024, on Cravenridge Drive.
THE START/END DATES ON THE SCHEDULE CAN CHANGE DAILY, PLEASE SEE THE MOST UPDATED SCHEDULE, BELOW.
ROADWAY MILLING AND RESURFACING OPERATIONS WILL INCLUDE MOST SATURDAYS!
2024 BROOKHAVEN ASPHALT PAVING SCHEDULE: UPDATED 07/02/24 | |||||
START DATE* | END DATE* | STREET NAME | FROM STREET | TO STREET | WORK TYPE |
05/28/24 | 05/28/24 | FERNWAY COURT | BYRNWYCK ROAD | CUL-DE-SAC | MILL & OVERLAY ASPHALT |
BY | 06/15/24 | BRETON CIRCLE | WOODROW WAY | RENNES DRIVE | MILL & OVERLAY ASPHALT |
05/31/24 | 06/03/24 | WOOD VALLEY COURT | JOHNSON FERRY ROAD | CUL-DE-SAC | MILL & OVERLAY ASPHALT |
BY | 06/15/24 | FRONTENAC COURT | WOODROW WAY | CUL-DE-SAC | MILL & OVERLAY ASPHALT |
BY | 06/15/24 | CLUB WALK DRIVE | HERMANCE DRIVE | CUL-DE-SAC | MILL & OVERLAY ASPHALT |
06/18/24 | 06/20/24 | HERMANCE DRIVE | TRAFFIC CIRCLE @ BROOKHAVEN AVENUE | MILL & OVERLAY ASPHALT | |
06/20/24 | 06/22/24 | CALDWELL ROAD | DRESDEN DRIVE | CHESHIRE WAY | MILL & OVERLAY ASPHALT |
06/24/24 | 06/28/24 | REDDING ROAD | CALDWELL ROAD | END OF ROAD (SOUTH) | MILL & OVERLAY ASPHALT |
06/28/24 | 07/10/24 | CRAVENRIDGE DRIVE | TRYON ROAD (S) | CALDWELL ROAD | MILL & OVERLAY ASPHALT |
07/11/24 | 07/12/24 | SKYLAND DRIVE | SKYLAND TRAIL | DRESDEN DRIVE | MILL & OVERLAY ASPHALT |
07/11/24 | 07/13/24 | CANMONT DRIVE** | SKYLAND DRIVE | CLAIRMONT ROAD | MILL & OVERLAY ASPHALT |
07/13/24 | 07/15/24 | RAVEN HILL DRIVE** | STOLAND DR | CLAIRMONT ROAD | MILL & OVERLAY ASPHALT |
07/15/24 | 07/16/24 | GARDENSIDE COURT | SKYLAND TRAIL | DEAD END | MILL & OVERLAY ASPHALT |
07/16/24 | 07/18/24 | EWING DRIVE | CORTEZ LANE | DREW VALLEY ROAD | MILL & OVERLAY ASPHALT |
07/18/24 | 07/19/24 | PINECONE LANE | DOUBLEGATE DRIVE | DEAD END | MILL & OVERLAY ASPHALT |
07/19/24 | 07/20/24 | LOGAN CIRCLE | BRIARWOOD ROAD | DEAD END | MILL & OVERLAY ASPHALT |
07/22/24 | 07/23/24 | LANIER DR (S'BOUND)** | WINDSOR PARKWAY | PEACHTREE ROAD | MILL & OVERLAY ASPHALT |
07/23/24 | 07/24/24 | CLUB PLACE | MABRY ROAD | CUL-DE-SAC | MILL & OVERLAY ASPHALT |
07/24/24 | 07/26/24 | HAVENBROOK WAY | OSBORNE ROAD | CUL-DE-SAC | MILL & OVERLAY ASPHALT |
07/26/24 | 07/26/24 | HARTS MILL ROAD | ASHFORD-DUNWOODY ROAD | WASSON WAY | MILL & OVERLAY ASPHALT |
07/27/24 | 07/29/24 | CHIPPEWA PLACE** | NAVAJO TRAIL | CHIPPEWA PL (CUL-DE-SAC | MILL & OVERLAY ASPHALT |
07/30/24 | 08/02/24 | CANDLER LAKE WEST | W NANCY CREEK DR | LONG BRANCH COURT | MILL & OVERLAY ASPHALT |
07/22/24 | 07/24/24 | LONG BRANCH COURT | CANDLER LAKE WEST | CUL-DE-SAC | FULL-DEPTH RECLAMATION |
MURPHY CANDLER COURT | CANDLER LAKE WEST | CUL-DE-SAC | MILL & OVERLAY ASPHALT | ||
CRANTON COURT | BERKFORD CIRCLE | CUL-DE-SAC | MILL & OVERLAY ASPHALT | ||
BRAWLEY WAY | BRAWLEY WAY/BRAWLEY CR | BERKFORD CIRCLE | MILL & OVERLAY ASPHALT | ||
BRAWLEY CIRCLE | BRAWLEY WAY/BRAWLEY CR (LOOPS) | MILL & OVERLAY ASPHALT | |||
DUNWOODY TRAIL | VICTOR ROAD | DUNWOODY PLACE | MILL & OVERLAY ASPHALT | ||
REMOVED | RESURFACING BY DEKALB CO. | ||||
* START/END DATES ARE TENTATIVE BASED ON WEATHER CONDITIONS AND OTHER UNFORESEEN CIRCUMSTANCES AND ARE SUBJECT TO CHANGE. | |||||
** A PORTION OF THIS WORK, AS SCHEDULED, FALLS ON A SATURDAY. | |||||
ROADWAYS IN PROGRESS. | |||||
CURRENTLY SCHEDULED 2024 ROADWAYS: START DATE AND TIMES ARE TENTATIVE. | |||||
COMPLETED 2024 ROADWAYS. | |||||
FUTURE 2024 ROADWAYS. | |||||
JUST ADDED | STREETS ADDED TO SCHEDULE AS OF 6/28/24 |
* | IF RESIDING ON A SCHEDULED ROADWAY, YOU WILL BE NOTIFIED, VIA HANDBILL, 48 HOURS BEFORE OPERATIONS BEGIN. |
** | MOST ASPHALT OPERATIONS WILL BE COMPLETED IN ONE TO TWO DAYS. |
*** | THE PAVING ACTIVITY WILL AFFECT LOCAL TRAFFIC AND LIMIT DRIVEWAY ACCESS TO HOMES DURING STATED WORKING HOURS; HOWEVER, THE CITY AND THE CONTRACTOR SHALL WORK TO MINIMIZE THIS INCONVENIENCE. |
**** | RESIDENTS AFFECTED BY ASPHALT OPERATIONS SHALL NOT PARK ON THE STREET BETWEEN ESTABLISHED WORKING HOURS (7 AM - 7 PM). |
***** | VEHICLES PARKED IN STREETS DURING ASPHALT OPERATIONS ARE SUBJECT TO TOWING AT VEHICLE OWNER'S EXPENSE. |
The adopted roads are listed in the following (tables or attachments), by year,
2024 (Phase 1): All 29 streets listed are to be milled and overlayed with 3-inches of asphalt, except for Murphy Candler Court, which will be a Full-Depth-Reclamation (FDR) process.
2025 (Phase 2): All 28 streets listed are to be milled and overlayed with 3-inches of asphalt, except for Ashton Woods Drive, Durden Dive, and Sunderland Way, which will be a Full-Depth-Reclamation (FDR) process.
2026 (Phase 3): All 19 streets listed are to be milled and overlayed with 3-inches of asphalt.
For more detail on the meaning of each in the process, follow this link to see Brookhaven’s Pavement Restoration Program Details Explained