2024 Paving Program

Paving Rehabilitation

REVIEWED/REVISED: 5/02/24

Brookhaven, GA, April 1, 2024 Competitive bids were opened on February 21, 2024, answering an invitation to contractors to bid on a three-year paving program for the City of Brookhaven. This award encompasses the paving program for the 2024, 2025, and 2026 years respectively. Over the three years specified, this project will impact 76 streets and 42.81 lane miles of Brookhaven roadways, and utilize SPLOST II (Special Purpose Local Option Sales Tax) funding.

**CW Matthews was awarded the three-year contract by the Brookhaven City Council on March 26, 2024.**

 

 

The 2024 Paving Project Commencement Date is Scheduled to Start on Monday, May 13, 2024.

 

2024 BROOKHAVEN ASPHALT PAVING SCHEDULE
START DATE* END DATE* STREET NAME FROM STREET TO STREET WORK TYPE
 
5/13/24 5/14/24 WOOD VALLEY COURT JOHNSON FERRY ROAD CUL-DE-SAC MILL & OVERLAY ASPHALT
5/15/24 5/15/24 FERNWAY COURT BYRNWYCK ROAD CUL-DE-SAC MILL & OVERLAY ASPHALT
5/15/24 5/20/24 BRETON CIRCLE WOODROW WAY RENNES DRIVE MILL & OVERLAY ASPHALT
5/20/24 5/22/24 FRONTENAC COURT WOODROW WAY CUL-DE-SAC MILL & OVERLAY ASPHALT
5/22/24 5/23/24 CLUB WALK DRIVE HERMANCE DRIVE CUL-DE-SAC MILL & OVERLAY ASPHALT
5/23/24 5/23/24 HERMANCE DRIVE TRAFFIC CIRCLE @ BROOKHAVEN AVENUE MILL & OVERLAY ASPHALT
5/23/24 5/24/24 LANIER DR (S'BOUND) WINDSOR PARKWAY PEACHTREE ROAD MILL & OVERLAY ASPHALT
    CLUB PLACE MABRY ROAD CUL-DE-SAC MILL & OVERLAY ASPHALT
    HAVENBROOK WAY OSBORNE ROAD CUL-DE-SAC MILL & OVERLAY ASPHALT
    CALDWELL ROAD DRESDEN DRIVE CHESHIRE WAY MILL & OVERLAY ASPHALT
    REDDING ROAD CALDWELL ROAD END OF ROAD (2958 Redding Rd) MILL & OVERLAY ASPHALT
    CRAVENRIDGE DRIVE TRYON ROAD CALDWELL ROAD MILL & OVERLAY ASPHALT
    SKYLAND DRIVE SKYLAND TRAIL DRESDEN DRIVE MILL & OVERLAY ASPHALT
    CANMONT DRIVE SKYLAND DRIVE CLAIRMONT ROAD MILL & OVERLAY ASPHALT
    RAVEN HILL DRIVE STOLAND DR CLAIRMONT ROAD MILL & OVERLAY ASPHALT
    GARDENSIDE COURT SKYLAND TRAIL DEAD END MILL & OVERLAY ASPHALT
    LOGAN CIRCLE BRIARWOOD ROAD DEAD END MILL & OVERLAY ASPHALT
    HARTS MILL ROAD ASHFORD-DUNWOODY ROAD WASSON WAY MILL & OVERLAY ASPHALT
    CHIPPEWA PLACE NAVAJO TRAIL CUL-DE-SAC MILL & OVERLAY ASPHALT
    CANDLER LAKE WEST W NANCY CREEK DR LONG BRANCH COURT MILL & OVERLAY ASPHALT
    LONG BRANCH COURT CANDLER LAKE WEST CUL-DE-SAC FULL-DEPTH RECLAMATION
    MURPHY CANDLER COURT CANDLER LAKE WEST CUL-DE-SAC MILL & OVERLAY ASPHALT
    CRANTON COURT BERKFORD CIRCLE CUL-DE-SAC MILL & OVERLAY ASPHALT
    BRAWLEY WAY BRAWLEY WAY/BRAWLEY CR BERKFORD CIRCLE MILL & OVERLAY ASPHALT
    BRAWLEY CIRCLE BRAWLEY WAY/BRAWLEY CR (LOOPS) MILL & OVERLAY ASPHALT
           
* START/END DATES ARE TENTATIVE BASED ON WEATHER CONDITIONS AND OTHER UNFORESEEN CIRCUMSTANCES AND ARE SUBJECT TO CHANGE.
           
  CURRENTLY SCHEDULED 2024 ROADWAYS.
  COMPLETED 2024 ROADWAYS.
  FUTURE 2024 ROADWAYS.

 

         * IF RESIDING ON A SCHEDULED ROADWAY, YOU WILL BE NOTIFIED, VIA HANDBILL, 48 HOURS BEFORE OPERATIONS BEGIN.

       ** MOST ASPHALT OPERATIONS WILL BE COMPLETED IN ONE TO TWO DAYS.

     *** THE PAVING ACTIVITY WILL AFFECT LOCAL TRAFFIC AND LIMIT DRIVEWAY ACCESS TO HOMES DURING STATED WORKING HOURS; HOWEVER, THE CITY

           AND THE CONTRACTOR SHALL WORK TO MINIMIZE THIS INCONVENIENCE.

   **** RESIDENTS AFFECTED BY ASPHALT OPERATIONS SHALL NOT PARK ON THE STREET BETWEEN ESTABLISHED WORKING HOURS (7 AM - 7 PM).

 ***** VEHICLES PARKED IN STREETS DURING ASPHALT OPERATIONS ARE SUBJECT TO TOWING AT VEHICLE OWNER'S EXPENSE.

 

 

The adopted roads are listed in the following (tables or attachments), by year,

2024 (Phase 1): All 29 streets listed are to be milled and overlayed with 3-inches of asphalt, except for Murphy Candler Court, which will be a Full-Depth-Reclamation (FDR) process.

2025 (Phase 2): All 28 streets listed are to be milled and overlayed with 3-inches of asphalt, except for Ashton Woods Drive, Durden Dive, and Sunderland Way, which will be a Full-Depth-Reclamation (FDR) process.

2026 (Phase 3): All 19 streets listed are to be milled and overlayed with 3-inches of asphalt.

 For more detail on the meaning of each in the process, follow this link to see Brookhaven’s Pavement Restoration Program Details Explained